What should holders of idle mining licences in Tanzania do after the TMIC 2026 warning? Prove work now. The Mining Act, Cap. 123 R.E. 2023, expects prospecting to start within three months and mining within eighteen months, and a default notice gives 30 days to remedy. A partner, service contract or offtake can fund that work without moving the licence. The Vice-President reaffirmed the raw-mineral export ban at TMIC 2026.

What changed at TMIC 2026
Idle mining licences Tanzania moved to the front of the agenda at the seventh Tanzania Mining and Investment Conference (TMIC), held at the Julius Nyerere International Convention Centre in Dar es Salaam from 19 to 21 November 2026. Vice-President Deogratius Ndejembi spoke for President Samia Suluhu Hassan. The Chanzo, on 20 November, reports that he said the export ban on unprocessed minerals will continue and that investors holding undeveloped licences will face action. The Respondent, on 19 November, reports that he told all licence holders to meet their permit obligations.
Minister Anthony Mavunde, quoted by The Chanzo, said "Not a single stone will leave the country unprocessed, unrefined or unpolished." The Chanzo also names strategic graphite, niobium, helium and nickel projects that have not started production. It reports an unnamed uranium licence holder in Namtumbo, Ruvuma, that had taken no steps to develop its mine, and says talks with that holder are going well.
One detail needs care. The Chanzo says the conference opened on "Thursday, November 20". In 2026, 20 November is a Friday and 19 November is the Thursday, which matches The Respondent's date. We use 19 November as the opening day and treat the Chanzo date as a slip.
What the law says
The governing text is the Mining Act, Cap. 123 R.E. 2023, which the Office of the Solicitor General publishes in its e-Library entry (Government Printer, 1 July 2025). The catalogue entry says it applies to Mainland Tanzania. We read the public PDF through section 73. We could not read section 74 or later in that file, so the table marks what we read and what we did not.
| Status | Proposition |
|---|---|
| Settled (read in the R.E. 2023 text) | A prospecting licence holder must begin within three months of grant, or a further period the licensing authority allows (s.46(1)). A mining licence holder must commence mining operations within eighteen months (s.62). A special mining licence has the same eighteen-month start with a further-period wording (s.57(1)(a)). |
| Settled (read) | No one may export a mineral unless they are a mineral right holder or a licensed dealer, and royalty and inspection fee are paid or secured (s.19(3)). The penalty as printed is TZS 10 million to 50 million or one to three years for an individual, and TZS 50 million to 100 million for a company (s.19(4)). Removal of minerals from a mine for export or domestic use needs the inspection conditions in section 115 (s.20). |
| Settled (read) | "Raw minerals" means minerals not yet processed, beneficiated or value added, and the meaning is subject to regulations on value addition (s.4). A mineral right holder must set aside minerals for processing, smelting or refining in the United Republic at a percentage the Minister sets (s.69, as printed in R.E. 2023). |
| Settled (read) | A special mining licence or mining licence cannot be assigned without written consent of the licensing authority (s.10(2)). No consent is needed for an assignment to a bank or financial institution by way of mortgage or charge given as security for a loan or guarantee for mining operations (s.10(3)(b)). Consent needs proof of substantial development, a Tax Clearance Certificate and cleared charges (s.10(4)). The application is on a prescribed form with a prescribed fee (s.10(5)). |
| Verify | Section 74 is headed "Suspension and cancellation of mineral right" in the arrangement of sections. We read its predecessor, section 63 of the 2019 consolidation, on TanzLII. It requires a default notice and gives 30 days from service, or longer if allowed, to remedy. Confirm the 2023 wording before you rely on it. |
| Verify | The 2024 Finance Act change to the set-aside. Our fee register records a gold set-aside of not less than 20% (register ID F0627). The R.E. 2023 section 69 we read leaves the percentage to the Minister. Confirm which text is in force. |
| Unknown | The exact provision for the raw-mineral export ban. The Chanzo cites "Section 100D". The arrangement of sections in R.E. 2023 has no section 100D, and the Act's controls over raw minerals sit in Part VII (ss.126 to 129). Whether 100D is a 2017 number, a later insertion or an error is not established. |
Our earlier guide to idle mining licences in Tanzania and the mining licence cancellation guide cover the legal route in depth. This page covers the deal questions that follow the conference.
Who should read this
Holders of prospecting, mining and primary mining licences who have not yet shown production. Investors, contractors and equipment owners who might partner with them. Licensed dealers, refiners and processors who buy from holders. Lenders and advocates advising any of them. Owners of idle excavators, crushers and trucks who want a licensed counterparty, on the idle assets room.
What did the Vice-President say, and what is still unknown?
Three reports give the same core message with different detail. The table keeps them apart.
| Point | Source and date | Status |
|---|---|---|
| Export ban on unprocessed minerals continues | The Chanzo, 20 November; The Respondent, 19 November | Reported by two outlets |
| Holders of undeveloped licences face action; government "will not hesitate" | The Chanzo, 20 November | Reported; no list, count or date |
| All holders must fulfil permit obligations | The Respondent, 19 November | Reported; no sanction, deadline or statute named |
| Royalty on locally refined gold cut from 6% to 4%; inspection fee and VAT waived through domestic mineral markets | The Chanzo, 20 November | Matches register IDs F0624, F0625 and F0627 for gold sold to refiners or the Bank of Tanzania |
| Licence holders must set aside at least 20% of output for local refining and trade | The Chanzo, 20 November | Verify. Our register records 20% for gold only (F0627) |
| Stepped-up inspections of licence holders | The Rio Times, 4 November, from one local report | Unconfirmed. The piece says Hansard was not online |
The conference reports name no deadline, no number of licences under review and no new notice. They cite no Gazette or Mining Commission document. Anyone who tells you a date is guessing.
Is section 100D the raw-mineral export ban?
We could not confirm it. The Chanzo says the Act's section 100D bars exports without value addition and that a concentrate export ban dates from March 2017. In the R.E. 2023 arrangement of sections that we read, the numbers run 100 to 110 for lapidary licences, with no lettered section. The 2017 amendments inserted lettered sections, and the 2023 revision renumbered the Act.
What the printed text does show is a layered control. Section 19(3) limits exporters to mineral right holders and licensed dealers who have paid royalty and inspection fee. Section 20 bars removal of minerals for export or domestic use unless the section 115 conditions are met. Section 69 requires a set-aside for local processing. Part VII adds storage (s.126), control over removal of raw minerals (s.128) and handling of mineral concentrates (s.129). We did not read those last three sections. Ask an advocate for the current text of the section the ban now sits in, and do not quote 100D in a contract.
What counts as an idle licence under the Act?
The Act does not use the word idle. It sets start duties, and a holder who misses them is in default. The table lists what we read.
| Licence | Start duty | Section (R.E. 2023) | Annual rent (register ID) |
|---|---|---|---|
| Prospecting licence | Begin within three months of grant; follow the attached programme; spend the prescribed minimum | s.46(1) | USD 100 per km2 in the first period (F0616); minimum spend USD 500 per km2 for most minerals (F0618) |
| Special mining licence | Begin mining within eighteen months or a further period allowed | s.57(1)(a) | USD 5,000 per km2 (F0621) |
| Mining licence | Commence mining operations within eighteen months; develop with due diligence | s.62 | USD 3,000 per km2 for metallic minerals (F0621) |
| Primary mining licence | No fixed start date found in the text we read; renewal tests diligence | ss.64 to 66 | TZS 90,000 per hectare for gold and gemstones, minimum TZS 180,000 under 2 hectares (F0620) |
Section 80 covers a holder suspending mining operations, and section 83 covers termination of a mining licence where production is insufficient. We read only their headings in R.E. 2023. The 2019 text, as summarised in our cancellation guide, sets a two-week notice for a planned suspension and a three-year, 50% output test for termination. Verify both against the 2023 text.
How does a default notice run before cancellation?
The sequence below follows section 63 of the 2019 text, now section 74 by heading. The Commission acts on non-primary rights after advice, and the holder can go to the High Court within 60 days of a decision. That appeal route was section 65 in 2019 and appears as section 76, "Appeals", in R.E. 2023.
| Step | What happens | Who acts |
|---|---|---|
| 1 | Breach of the Act, regulations, licence conditions or a direction | Holder |
| 2 | Default notice states the grounds | Licensing authority |
| 3 | 30 days from service, or longer if allowed, to remedy | Holder |
| 4 | Suspension or cancellation if not remedied; rights cease but earlier liabilities remain | Licensing authority |
| 5 | Judicial review within 60 days of the decision | Holder, through an advocate |
The 2026 enforcement follows this pattern. TanzaniaInvest, on 16 April, reported that the Minister cancelled 40 exploration licences on 15 April, covering about 188,163 acres, and gave 43 more holders 30 days to fix breaches. The grounds reported were failure to develop, unpaid fees, local content failures and unmet social responsibility duties. The Daily News reported on 16 September that Deputy Minister Steven Kiruswa warned holders of 33 jointly held licences in a Mwanza dispute, with no statute or deadline named. Disputes, seizure and prosecution go to an advocate.
Can a partner save an idle licence?
A partner cannot cure a legal default by name alone. A partner can fund and run the work that the licence requires, and that work is the evidence a holder gives the Commission. The routes differ in what they do to the licence.
| Route | What the partner supplies | Does the licence move? | Main check |
|---|---|---|---|
| Service or contract-mining agreement | Plant, crews, working capital, paid per tonne or per metre | No | Holder keeps control; start date and programme in the contract |
| Equipment hire | Excavators, crushers, trucks on a hire rate | No | Insurance, title papers, no lender charge without consent |
| Offtake with a licensed dealer or refiner | Purchase commitment and sometimes prepayment through the buyer's own bank | No | Dealer licence, royalty, inspection fee, domestic processing route |
| Joint venture company | Capital and expertise for a share of output or equity | Only if the licence is assigned, which needs consent for an ML or SML | Section 10; change of control (s.158, heading only read) |
| Assignment of the licence | Price for the right | Yes | Consent, Tax Clearance Certificate, cleared rent; eligibility of the buyer |
The guide to partnering on a PML and the mining joint venture guide set out the structures in detail. A primary mining licence is for citizens only (register ID F0619), so a foreign investor takes part by contract and never through a nominee. Fursa365 refuses nominee structures at screening.
Can an idle licence be transferred or charged to bring in a partner?
Yes, with conditions. Under section 10(1) a holder may assign a mineral right or an undivided share of it. For an ML or SML, section 10(2) requires the licensing authority's written consent, and section 10(4) refuses consent unless substantial development is proved, a Tax Clearance Certificate exists and other charges are cleared. A holder with no development cannot meet the first test, so an idle ML is hard to sell on its own merits.
A bank charge is the exception. Section 10(3)(b) removes the consent step for a mortgage or charge to a bank or financial institution as security for a loan or guarantee for mining operations. The loan security guide covers what lenders do with that and cites the 2019 number, section 9(3)(b). In R.E. 2023 the same rule is section 10(3)(b), as we read it. The Mining Commission fee for transfer of a non-PML right is USD 3,000 and for a PML transfer TZS 500,000 (register IDs NEW-06-16 and F0619). Fursa365 never lends and never holds money. Any consideration moves between the parties through their banks.
What should a buyer or processor check before taking ore?
Buyers carry their own risk. The checks below follow the sections we read.
- Licence status. Ask for a dated Mining Cadastre printout, the latest rent receipt and a statement that no default notice is open. A cancelled licence leaves the buyer with minerals nobody may lawfully supply.
- Who may export. Only a mineral right holder or licensed dealer may export, after royalty and inspection fee (s.19(3)). A mineral dealer licence application is USD 200 (register ID F0622), and an export permit application is USD 100 (register ID F0628).
- The processing route. A raw-mineral buyer should ask how the lot meets the domestic processing rule. A processing, smelting or refining licence application is TZS 150,000 (register ID F0631).
- Chain of title. Trace the lot to a mine, a licence and a royalty payment. Provenance gaps carry money-laundering risk.
- Local content and ownership. Parts of the Act on local content and the integrity pledge (ss.133 to 137) were read by heading only. See the ownership checks guide.
Fursa365 does not deal in minerals, take title or settle sales. It introduces a licence holder and a verified licensed counterparty, and the parties settle direct. The mineral offtake guide explains the agreement.
A worked example: a gold mining licence with no output after 20 months
Illustrative figures, not a quote or a price forecast. A Tanzanian-owned company holds a mining licence for gold over 4 km2, granted 20 months ago. It has surveyed but not mined. The eighteen-month start period has passed. It has no capital for plant and expects a default notice.
| Item | Working | Amount |
|---|---|---|
| Annual rent, metallic ML (F0621) | 4 km2 at USD 3,000 (TZS 6,800,000) | USD 12,000 (TZS 27,200,000) |
| Transfer of the licence, if sold (NEW-06-16) | Avoided if the partner contracts and does not take the licence | USD 3,000 |
| Assumed gross value of first sales | Illustrative, not a gold price | USD 500,000 |
| Royalty at 6% (F0624) | 6% of 500,000 | USD 30,000 |
| Inspection fee at 1% (F0625) | 1% of 500,000 | USD 5,000 |
| HIV Response Levy (F0626) | 0.1% of 500,000 | USD 500 |
| Total, ordinary route | 30,000 + 5,000 + 500 | USD 35,500 |
| Total, gold sold to a refinery centre or the Bank of Tanzania (F0624, F0625, F0627) | 4% royalty, 0% inspection fee, plus levy | USD 20,500 |
The holder signs a contract-mining agreement with a plant owner, who brings an excavator and crusher on hire and a crew, and agrees a start date inside the 30-day remedy window. It sends the Commission a letter of commitment with the programme and the contract. The refinery route saves USD 15,000 on this assumed value, or 3% of gross, but only if the conditions of the programme are met. Income tax, VAT and withholding are for an accountant. Government charges are paid at the official rate to the Mining Commission and stay separate from any professional fee.
Mainland or Zanzibar: which rules apply?
The Mining Act, Cap. 123, applies to Mainland Tanzania, according to the OSG catalogue entry. Zanzibar has its own laws and institutions, and a Mainland licence does not carry into Zanzibar. We did not verify how minerals or licences are regulated there, and we found no source that applies the Vice-President's statements to Zanzibar. A deal touching Zanzibar needs an advocate admitted on that side and a separate check.
What to do now
- Pull the licence file. Print the Cadastre status, grant date, programme, rent receipts and any notice. Work out the three-month or eighteen-month start date from the grant date.
- Answer any notice inside 30 days. Send a written response with evidence of work and a start date. An advocate handles any dispute or appeal.
- Show real work. Survey, sampling, pits, payroll and equipment hire records count more than a plan. Keep dated photographs and invoices.
- Choose the route. Service contract, hire, offtake, joint venture or assignment. Prefer routes that leave the licence with the holder unless a sale is the aim.
- Check eligibility and ownership. A PML goes to citizens only. Disclose every beneficial owner. Refuse nominee arrangements.
- Price the government charges separately. Rent, royalty, inspection fee and levy come from the register at the official rate. An accountant confirms tax.
- Get your own expert reports. A geologist or valuer instructed by you, not by the counterparty. Zatra does not value assets. See the independent expert guide.
- List on Fursa365 and match. Post the offer or request with an end date, let Zatra screen it, then review the verified counterparties it proposes.
- Sign the NDNCA before names move. See NDNCA explained.
- Sign an advocate-drafted agreement before any equipment, money or ore moves. Fees are paid under a PSFA as set out on fees.
Key dates
| Date | Event | Source |
|---|---|---|
| 15 April 2026 | 40 exploration licences cancelled; 43 holders given 30 days | TanzaniaInvest, 16 April 2026 |
| 18 July 2026 | Minister warns undeveloped licences will be revoked and reallocated | The Citizen, 18 July 2026 |
| 15 September 2026 | Deputy Minister warns holders of 33 joint licences in Mwanza | Daily News, 16 September 2026 |
| 4 November 2026 | Reported stepped-up inspections of licence holders | The Rio Times, single local report |
| 19 to 21 November 2026 | TMIC 2026, Dar es Salaam | The Respondent; The Chanzo |
| Notice date plus 30 days | Remedy period on a default notice | Mining Act, 2019 s.63 (R.E. 2023 s.74) |
| Decision date plus 60 days | Judicial review window | Mining Act, 2019 s.65 (R.E. 2023 s.76) |
The Minister's July warning came at an event issuing mining licences to small-scale miners in Mwanza, according to The Citizen, which cited no statute or deadline. No new deadline followed the conference.
How Zatra helps
Zatra Consultants Limited screens a holder's licence file and a partner's capacity, verifies identity, ownership and licence status before a match, and structures the contract, hire, offtake or joint venture. The wider group runs in order: Fursa365 matches, Zatra structures, NEMBO packages and Kasongo Auction Mart auctions. Zatra does not insure, license, value, lend or hold money, and does not decide or guarantee any authority's outcome. The Mining Commission decides licence matters.
Two cost buckets stay apart. Government fees at the official rate, such as rent, royalty and transfer fees, are paid to the authority and listed in the government fees register. Zatra's professional fee is separate and falls under a PSFA, as a professional fee and not brokerage. Fursa365 is not a marketplace and does not deal in minerals, as the regulatory boundaries page says. Introductions use verification, business deals, project participation and deal rounds. Disputes, seizure, prosecution and legal opinions go to an advocate. Tax questions go to an accountant such as CPA Altho Mwangoa. Zatra Consultants Limited is the PDPC-registered data controller for member data.
Sources and status
Accurate as at 23 Nov 2026. Figures are from the sources below and from the Zatra government fees register, quoted with their register IDs so they can be checked line by line.
- The Mining Act, Cap. 123 R.E. 2023, full text (ss.4, 10, 19, 20, 46, 57, 62, 69 read). Office of the Solicitor General e-Library, Government Printer, published 1 July 2025. Accessed 23 Nov 2026.
- Mining Act, Cap. 123, consolidation as at 30 November 2019 (ss.63, 65). TanzLII, 30 November 2019. Accessed 23 Nov 2026.
- Tanzania reaffirms ban on raw mineral exports, warns firms sitting on idle licences. The Chanzo, 20 November 2026. Accessed 23 Nov 2026.
- Tanzania warns mining firms over licence breaches, pushes local processing. The Respondent, 19 November 2026. Accessed 23 Nov 2026.
- Tanzania Steps Up Checks on Mining Licences. The Rio Times, 4 November 2026, citing one local report. Accessed 23 Nov 2026.
- Tanzania cancels 40 mineral exploration licenses and returns 188,163 acres. TanzaniaInvest, 16 April 2026. Accessed 23 Nov 2026.
- Tanzania cautions mining licence owners against leaving their sites undeveloped. Daily News, 16 September 2026. Accessed 23 Nov 2026.
- Mining minister expands crackdown on idle mining licences. The Citizen, 18 July 2026. Accessed 23 Nov 2026.
- Zatra Tanzania Government Fees Register 2026 (F0616 to F0631, NEW-06-16). Zatra Consultants Limited, 2026 edition. Accessed 23 Nov 2026.
Figures to confirm before you act
- Section 74 wording in R.E. 2023 (suspension and cancellation): read only as section 63 of the 2019 text; confirm the 30-day remedy and the Commission-advice step
- Section 100D: not found in the R.E. 2023 arrangement of sections; confirm which provision carries the raw-mineral export ban
- Set-aside percentage under section 69: Minister sets it in the R.E. 2023 text we read; the register records not less than 20% for gold (register ID F0627); the Chanzo reports 20% of output generally
- Rent, royalty, inspection fee and levy: ML rent USD 3,000 per km2 (F0621), royalty 6% or 4% (F0624, F0627), inspection fee 1% or 0% (F0625, F0627), levy 0.1% (F0626)
- Transfer fees: non-PML right USD 3,000 (NEW-06-16), PML TZS 500,000 (F0619); mineral dealer application USD 200 (F0622); export permit USD 100 (F0628); processing licence application TZS 150,000 (F0631)
- Gross value of USD 500,000, the 3% saving and any joint venture split: illustrative only
- TMIC opening date: 19 November per The Respondent; the Chanzo says Thursday 20 November, which is a Friday
General information prepared by the Fursa365 deal desk, Zatra Consultants Limited. It is not legal, tax or investment advice and does not decide or guarantee any authority's outcome. Confirm current rules and fees with the authority named and your own advocate before you act. Mainland Tanzania is described; Zanzibar has separate laws and bodies.
Questions readers ask
Can the Mining Commission cancel my licence without warning?
The 2019 text, now section 74 by heading, requires a default notice stating the grounds and 30 days from service, or longer if allowed, to remedy. A disqualified holder follows a separate route. Confirm the 2023 wording with an advocate, and answer any notice in writing within the period.
Does the export ban stop me selling concentrate abroad?
Unknown on the sources read. The Act defines raw minerals subject to regulations on value addition, and section 19(3) limits exporters to licence holders and dealers who pay royalty and inspection fee. The concentrate rules were not read here. Ask an advocate for the current regulation before any shipment.
Can a foreign investor partner with a PML holder?
By contract, yes, for example equipment supply, services or offtake through a licensed dealer. The register marks the PML as not available to foreigners (F0619). Control through a nominee or side agreement is unlawful, and Fursa365 refuses such structures at screening.
Does a joint venture protect me from cancellation?
No. Cancellation turns on the holder's compliance. A joint venture helps only if it funds and delivers the programme, and the evidence reaches the Commission. Put the start date, the programme and a cure plan for any default notice into the written agreement.
Do I need Mining Commission consent to sell an idle licence?
For a special mining licence or mining licence, yes (s.10(2)). Consent requires proof of substantial development, a Tax Clearance Certificate and cleared charges (s.10(4)). A primary mining licence follows its own rules, so confirm the process and fee with the Commission before you agree a price.
Will Fursa365 sell my ore or hold the money?
No. Fursa365 never holds money, never lends and is not a marketplace. It matches a licence holder with a counterparty that Zatra has verified. Sales happen between licensed parties, who settle through their own banks under an agreement an advocate drafts.
Who pays the Mining Commission fees in a partnership?
The agreement decides, but the Commission looks to the licence holder for rent and royalty. State in writing who pays each charge, when, and what happens on late payment. Government fees are paid at the official rate and sit apart from Zatra's professional fee.
What if I get a notice and cannot start work in 30 days?
Reply in writing before the period ends with evidence of work, a dated programme and any signed partner contract, and ask for more time as the Act allows. If the Commission cancels, an advocate can file for judicial review within 60 days of the decision.