Mining desk · Environment

EIA certificate Tanzania: NEMC approval, categories, fees and what a project partner must check.

What a partner joining a Tanzanian project must check on its environmental impact assessment certificate: categories, who applies, NEMC fees, timing, transfer on a change of owner, mining projects and Zanzibar.

Engineers reviewing plans on site
DEAL DESK GUIDE
16minute read
16sources cited
8questions answered
Direct answer

Who issues an EIA certificate in Tanzania, and does it pass to a new owner or JV partner? On the Mainland the Minister responsible for environment issues the certificate on the recommendation of NEMC, and the study must come before construction or financing. If the project changes owner, the certificate may be transferred on written notice to the Minister within 30 days. A share purchase leaves the holder unchanged. Zanzibar has its own authority, ZEMA, and its own Act.

Engineers reviewing plans on site
A certificate attaches to one described project on one site. A partner who joins should read its conditions against what is being built.

What the law says

An EIA certificate Tanzania projects need is issued under the Environmental Management Act, 2004 (Act No. 20 of 2004, Cap. 191), Part VI, sections 81 to 103. The National Environment Management Council (NEMC) screens and reviews. The Minister responsible for environment approves and signs. This guide is written by Eng. Dennis Wilson for the Fursa365 Project participation desk. It covers Mainland Tanzania, with Zanzibar in its own section.

In the enacted text, section 81(1) obliges the proponent or developer of a Third Schedule project to carry out an assessment at their own cost. Section 81(2) puts the study before commencement or financing. Section 81(3) says a licence or permit under another law does not replace the certificate. Section 84(1) says the certificate is no defence in later legal proceedings. The Environmental Management (Amendment) Act, 2025 (Act No. 5 of 2025) added climate functions and, as read, left sections 81 to 102 untouched.

Procedure sits in the Environmental Impact Assessment and Audit Regulations, GN 349 of 2005, as amended by GN 474 of 2018. NEMC fees are in GN 387 of 2021 and its later amendments. The table sorts each proposition into settled, verify or unknown.

PropositionStatusBasis
Study before commencement or financing; a licence does not replace the certificateSettledEMA s.81(2), (3)
Categories A, B1, B2 and SpecialSettledGN 474 of 2018, reg 4A
Transfer on change of ownership, notified to the Minister within 30 daysSettledEMA s.84(2); GN 349 reg 36
NEMC application, review and transfer feesSettledGN 387 of 2021; register F0495 to F0501
Whether the 2004 wording of s.84 survives unchanged in the 2019 revised Cap. 191VerifyRevised edition not read
How long a Mainland certificate lastsVerifyRegulations silent; one sample says life of project
Whether a share sale needs any NEMC noticeVerifyInference from s.84(2); ask NEMC in writing
Penalty for starting without a certificate (s.81(4))UnknownNo amount in the text read
Typical elapsed time from registration to certificateUnknownNo published average found

Who should read this

Investors and operators asked to join a plant, mine, quarry, farm, hotel, depot or road project that already has, or still needs, an environmental certificate. Owners of idle sites weighing a sale or a joint venture. Lenders and contractors who want to see the file before they commit. Advocates drafting the sale or JV agreement.

Which projects need an EIA certificate, and what are the categories?

Regulation 4A, inserted by GN 474 of 2018, sorts projects by the magnitude of environmental impact into four categories. The First Schedule lists the projects in each, in 22 sectors for Type A, 19 for Type B1 and 11 for Type B2. The list decides, not the investor's view of the project's size.

CategoryMeaningExamples as printed in the First Schedule
Type AMandatory EIALarge and medium mines; oil and gas field development, pipelines and refineries; thermal or hydro power of 50 MW or more; cultivation of 100 ha or more; housing estates; industrial parks; trunk road construction
Type B1Borderline: screening decides if a full EIA is neededSmall-scale mines; filling stations and product depots; power below 50 MW, solar and onshore wind; cultivation of 50 to under 100 ha; major urban projects
Type B2Non-mandatory: project brief and registrationCultivation of 10 to under 50 ha; schools under 360 students; camping
SpecialTreated as Type AIntroducing alien tree species into forest plantations

The Act's Third Schedule was not reproduced in the copy read, so the First Schedule above comes from the 2018 amendment text. For the broader screening question see the Zatra note on when an EIA is required.

Who applies, and who signs the certificate?

The proponent or developer applies. Section 3 defines a proponent as a person proposing or executing a project, so an operating partner can be a proponent as well as the land owner. Regulation 5(3) requires an application form, the prescribed fee and the relevant information. Regulation 6(2) requires a registered environmental expert to prepare the project brief. Regulation 4(4) issues the certificate once land ownership and the project location are proved.

The Third Schedule sets the forms: Form 1 for the application, Form 2 for a Type B2 project brief and Form 4 for the scoping report of a Type B1 or Type A project. NEMC runs an EIA online system, and its website lists registered experts. NEMC reviews and recommends. Section 92 gives the Minister 30 days from the Council's recommendation to approve, disapprove or approve with conditions. An aggrieved person may appeal to the Environmental Appeals Tribunal under section 95.

What does NEMC charge for an EIA certificate?

These are government fees at the official rate. They are paid to the authority and are separate from any professional fee. All lines are in the Zatra fee register, fees at 26 September 2026.

ItemAmount (TZS)Register ID
EIA application; project brief or scoping report submission50,000; 150,000F0495
Certificate reprint; transfer; surrender; variation300,000; 300,000; 300,000; 150,000F0496
Review, Type A extractive, by project cost5 million below 1 billion, rising through 8, 8.5, 20 and 50 million to 100 million at 500 billionF0498
Review, other Type A4 million below 1 billion, rising through 6, 6.5, 15 and 30 million to 70 million at 500 billionF0499
Review, Type B2 million below 50 million; 3 million from 50 to 99.99 million; 4 million above 100 millionF0500
Government-financed community projects0.05% of cost, minimum 5 million, maximum 50 millionF0501
Annual compliance monitoring and audit feeSet by sector; due 1 July; 5% a month if paid after 31 December; not refundableNEW-05-01, F0504 to F0510

GN 387 prints a single Type B band. Whether it applies to both B1 and B2 files is marked verify. The register shows no band between TZS 99.99 million and 100 million, so confirm the fee for a project at that cost. Expert fees and the cost of the study are not government fees and are not in the register, so they are unknown here and must be quoted.

How long does approval take, and how long does a certificate last?

The regulations fix clocks for NEMC and the Minister, but they run on a complete file. No source read publishes an average end to end, so the elapsed time is unknown. Ask the expert for the dates on their last three comparable files before you set a closing date.

StepClockBasis
Type B2 project brief examined14 daysReg 7(1) as amended 2018
Scoping report and terms of reference scrutinised14 daysRegs 8(6), 10(6)
Type B1 screening decision, with reasons21 days from the project briefReg 9
Council review of the impact statement60 days from submissionEMA s.87(1)
Minister's decision after recommendation30 daysEMA s.92
Provisional environmental clearance4 months, non-renewable, mobilisation only, not transferableReg 13; Form 5
Documents lodged while an application is pendingValid for 2 years, then may be deregisteredReg 41A
Start of development after the certificateWithin 3 years, or re-registerGN 349 reg 41

The amended regulations state no validity period for the certificate itself. A Government of Tanzania certificate form, quoted in a JICA-hosted file, reads that it is valid for the whole life cycle of the project unless revoked or suspended, and that the Minister must be notified of any transfer, variation or surrender. Treat that as one sample and read the conditions on the certificate you are shown.

What happens to the certificate when a project changes hands or a JV partner joins?

The answer depends on how the partner joins. Section 84(2) allows the certificate to pass from one holder to another when the project changes ownership, on written notice to the Minister within 30 days of the transfer. Regulation 36 of GN 349 adds that the transfer is only for the project the certificate was issued for. It also says the transferee and transferor are both liable for obligations under the certificate, but the transferor is not liable for later ones. The two parties notify the Minister jointly in Form 7, and the Minister issues a certificate of transfer in Form 8. The 2018 amendments, as read, do not touch these rules.

How the partner joinsCertificate positionCost and clock
Buys shares in the company that holds the certificateHolder unchanged. Section 84(2) is not triggered on its face, but liabilities stay in the company. Confirm with NEMC in writing (verify)No NEMC fee stated
Project, site or licence moves to a new company or SPVTransfer under s.84(2) and reg 36, Forms 7 and 8TZS 300,000 (F0496); notify within 30 days
Partner becomes operator while the owner keeps titleNot addressed in the texts read. Ask NEMC whether it is a transfer or a change notified under reg 42(1)Unknown
Joint venture expands capacity or changes the processVariation (reg 35, Forms 5 and 6) or a fresh study if the change is substantial (s.97)TZS 150,000 (F0496); a fresh study pays a new review fee
Certificate issued but nothing built for 3 yearsRe-register the intention to develop (reg 41)Fee for re-registration unknown

Section 97 lets the Council require a fresh study at any time after issue if the project changes substantially, new threats emerge or the earlier information was false or misleading. Section 98 makes it an offence to ignore that direction. A partner who inherits a certificate therefore inherits its history. For the share route see share transfer filings and when to form an SPV.

Is a mining project treated differently from other projects?

Yes, in four ways. First, large and medium mines are Type A, so a full study is mandatory, and small-scale mines are Type B1. Second, the Mining Act ties the mineral right to the certificate. In the consolidated text to 30 November 2019, a special mining licence application includes the applicant's environmental certificate (s.41(3)(e)), its renewal needs one (s.45(2)(e)), and a missing certificate is a ground to refuse a mining licence (s.50(1)(vi)). A primary mining licence application needs an environmental protection plan under s.54(3)(d). Whether later amendments changed these sections is verify.

Third, the fees differ. Extractive Type A review fees are higher (F0498), and a major mining works annual fee is TZS 4,500,000 (F0505). Category 16 adds environmental fees on minerals produced, such as 0.5% of gross value for gold at the point of sale (NEW-05-04). Fourth, a mineral right and the certificate move on separate tracks. Assigning a special mining licence or mining licence needs written consent of the licensing authority under s.9 of the Mining Act, which is not a NEMC transfer. Both files must be complete.

See partnering on a PML, mine closure guarantees, mining joint ventures and the Zatra notes on mining obligations after the certificate and mining licence transfer.

Worked example: a partner joins a processing plant

This worked example is illustrative. An owner holds a Type A certificate for a TZS 12 billion non-extractive processing plant. A partner can buy 49% of the company's shares, or buy the plant into a new SPV. Assume the file is Type A and the plant sits in the TZS 10 billion to 49.99 billion review band.

LineAmount (TZS)Register ID
Fees had the plant needed a new certificate: application 50,000, project brief 150,000, review 15,000,00015,200,000F0495, F0499
Same file if the project were extractive: review 20,000,00020,200,000F0495, F0498
Share route: NEMC transfer fee0 statedNone
SPV route: transfer of certificate300,000F0496
Later capacity variation150,000F0496
Annual compliance fee if the plant is cement, per year4,500,000F0508
Penalty if that fee is paid after 31 December, per month, if charged on the unpaid fee225,000NEW-05-01

The fees are small beside the plant. The risk lies elsewhere. If the plant has grown to 15 billion of capacity without a variation, the share route buys that breach with the company. The SPV route moves the certificate but carries the same history. Both routes need the price, warranties and indemnities to reflect it.

Mainland and Zanzibar: two separate regimes

Mainland and Zanzibar have separate Acts and separate authorities. A group working on both sides of the channel should plan two files and confirm any reciprocity in writing. Zanzibar's Act is the Zanzibar Environmental Management Act No. 3 of 2015. The Zanzibar Environmental Management Authority (ZEMA) reviews and issues. Some Zanzibar points rest on a project-promotion page and guides rather than the Act text, so they are marked.

PointMainlandZanzibar
StatuteAct No. 20 of 2004, Cap. 191Act No. 3 of 2015
AuthorityNEMC reviews; Minister signsZEMA reviews and issues the certificate
CategoriesA, B1, B2, Special (reg 4A)ZEMA screening sets the level; categories not confirmed
Where to startNEMC online systemZEMA officer at the ZIPA One Stop Centre
Registration feeTZS 50,000 application (F0495)TZS 200,000, non-refundable, per the ZIPA page; not in the register
Review feeBy cost band (F0498 to F0500)Charged; amount not stated
ValidityVerify; read the conditionsFive years per the ZIPA page
ExpertRegistered with NEMCRecognised by ZEMA
Transfer on change of owners.84(2); TZS 300,000Unknown

ZEMA's general terms of reference (October 2021) cite Environmental Assessment Regulations of 2019. Two older guides cite the 2002 procedures regulations, so which text is in force is verify. The ToR requires an audit after five years of operation. Independent summaries by the Netherlands Commission for Environmental Assessment and a DBSA draft handbook describe ZEMA's screening, comment periods and appeal route. A Zanzibar project also needs investor registration; see ZIPA registration. Use an advocate admitted in Zanzibar for any dispute.

What should a partner check before signing?

CheckAsk forWhy it matters
Holder and projectCertificate with all conditions and annexesName, site, capacity and process must match the deal
StageApproved EIS, or only registration or provisional clearanceProvisional clearance allows mobilisation only and cannot be transferred
Start dateDate construction beganThree years without a start means re-registration
Annual feeReceipts for each 1 July feeLate fees run at 5% a month
Monitoring and auditAnnual reports and audit reportsSs.99 to 101 give the Council monitoring and audit powers
Changes since issueVariation certificates, capacity recordsSubstantial change can trigger a fresh study
Land proofTitle and land rent receiptsThe certificate issues once land ownership is proved
ExpertRegistration number of the signing expertCheckable on NEMC's list of experts

Put the checks into the data room under the NDNCA, as the data room guide describes, and use the independent expert guide to choose who reads the reports. The verification page shows what Zatra checks. The general company checks are in verify a company before a deal.

What to do now

  1. Identify the category against the First Schedule with the expert: Type A, B1, B2 or Special, and whether the project is extractive.
  2. Get the full certificate file: certificate, conditions, impact statement approval letter, variations and annual reports, and confirm the holder is your counterparty.
  3. Test the project against the certificate: site, capacity, process and start date, and ask whether a variation or fresh study is due.
  4. Choose the joining route with an advocate: shares, SPV or operator, and write the 30-day transfer notice and Forms 7 and 8 into the closing steps.
  5. Put the open questions to NEMC or ZEMA in writing: share sale notice, operator change, validity, and the review fee band.
  6. List the project or the stake on Fursa365 with the category, stage and certificate status stated, so verified partners can see it, and accept a match.
  7. Sign the NDNCA before the certificate number, site coordinates, reports or names move.
  8. Sign an advocate-drafted agreement that makes closing conditional on the transfer or confirmation, allocates the fees and the cost of any fresh study, and gives indemnities for past non-compliance, with payment by bank transfer to the seller's own account.

Key dates

ItemWhen
Notify the Minister of a transferWithin 30 days of the transfer (s.84(2))
Start development under an issued certificateWithin 3 years, or re-register (reg 41)
Provisional environmental clearance4 months, not renewable (reg 13)
Annual NEMC compliance fee1 July; 5% a month after 31 December
Zanzibar certificateValid five years per the ZIPA page; audit after five years of operation
Fees in this guideRegister at 26 September 2026, including GN 158O of 2026 in force 1 July 2026

How Zatra helps

Zatra Consultants Limited screens the certificate file before a project is shown, and verifies the partner's identity and capacity before a match. It structures the deal as the client's adviser under a PSFA and coordinates the environmental expert, the advocate and the accountant. Fursa365 matches qualified offers to demand that Zatra has verified. It is not a buy-and-sell marketplace, and introductions are not employment agency or estate agency activity.

Zatra does not insure, license, value, lend or hold money, and it does not decide or guarantee any authority's outcome at NEMC, ZEMA, the Minister, the Mining Commission or TISEZA. The success fee is a professional fee to Zatra under a PSFA, not brokerage. Government fees at the official rate, such as the NEMC lines above, are a separate cost bucket from Zatra's professional fee, as the fees page and the note on professional and government fees explain. Zatra Consultants Limited is the PDPC-registered data controller for personal data in a listing.

Use an advocate for a dispute, seizure, prosecution or legal opinion, and an accountant for tax, such as CPA Altho Mwangoa. The professional panel lists both. Start from project participation, see idle assets, business deals, deal rounds and skills, and read the NDNCA guide. The wider structure is in the JV agreement guide, and an auction suits a disposal with a fixed date.

Sources and status

Accurate as at 27 Nov 2026. Figures are from the sources below and from the Zatra government fees register, quoted with their register IDs so they can be checked line by line.

Figures to confirm before you act

  • Transfer: notify the Minister within 30 days (s.84(2)); TZS 300,000 (F0496); Forms 7 and 8
  • Application TZS 50,000 and project brief or scoping report TZS 150,000 (F0495)
  • Variation TZS 150,000, reprint and surrender TZS 300,000 (F0496)
  • Review fees by project cost: extractive Type A (F0498), other Type A (F0499), Type B (F0500), community projects (F0501)
  • Annual compliance fee due 1 July, 5% a month after 31 December (NEW-05-01); major mining works TZS 4,500,000 (F0505); cement TZS 4,500,000 (F0508)
  • Review clocks: 14, 21, 60 and 30 days; three-year start rule (reg 41); two-year pending rule (reg 41A)
  • Mainland certificate validity, and whether Type B fees cover B1 and B2
  • Zanzibar registration TZS 200,000 and five-year validity (ZIPA page); which Zanzibar regulations are in force
  • Mining Act ss.41(3)(e), 45(2)(e), 50(1)(vi) after any amendment since 2019
  • Worked example: TZS 12 billion plant, fees TZS 15,200,000 or 20,200,000

General information prepared by the Fursa365 deal desk, Zatra Consultants Limited. It is not legal, tax or investment advice and does not decide or guarantee any authority's outcome. Confirm current rules and fees with the authority named and your own advocate before you act. Mainland Tanzania is described; Zanzibar has separate laws and bodies.

Questions readers ask

Is an EIA certificate needed before a mining licence?

For a special mining licence, the Mining Act text read lists the applicant's environmental certificate among the application contents, and a missing certificate is a ground to refuse a mining licence. A primary mining licence needs an environmental protection plan. Confirm the current text with the Mining Commission.

Can I start building while the EIA is pending?

No. Section 81(2) requires the study before commencement or financing, and a licence does not replace the certificate. A provisional environmental clearance allows mobilisation only, lasts four months and cannot be renewed or transferred. Starting works is an offence risk and a financing risk.

Does a share purchase transfer the EIA certificate?

On its face no, because the holder company is unchanged and section 84(2) speaks of the project changing ownership. The buyer inherits the company's history, including breaches. Ask NEMC in writing whether any notice is needed, and cover past non-compliance by indemnity.

What if the certificate holder will not cooperate on a transfer?

Regulation 36 requires the transferee and transferor to notify the Minister jointly, and if they do not, the registered holder is deemed the person in charge. Make the notice and Forms 7 and 8 a signing deliverable, and use an advocate if the seller refuses.

How much does NEMC charge to review a TZS 5 billion project?

A TZS 5 billion project falls in the 5 to 9.99 billion band, so the review fee is TZS 6.5 million for a Type A project or TZS 8.5 million if extractive, plus the TZS 50,000 application and TZS 150,000 brief fees. Type B projects pay TZS 2 to 4 million.

Does a Mainland certificate work in Zanzibar?

The sources read treat the two regimes as separate, with ZEMA under the 2015 Zanzibar Act for the islands. No source read says one certificate covers both. Plan two files and confirm with ZEMA and NEMC before assuming reciprocity.

Who prepares the impact assessment?

A registered environmental expert prepares the project brief on the Mainland, and the proponent pays. In Zanzibar the expert or firm must be recognised by ZEMA. Check the expert's registration number on the authority's list before you rely on the report.

What happens if the project is not built within three years?

Under regulation 41 of GN 349, a developer who has not started within three years of the certificate must re-register the intention to develop with the Council. The fee for that step is not stated in the register, so ask NEMC before the three years run out.

Seen an error or a changed fee? Write to [email protected] with the guide title and the line. The desk reviews every guide quarterly and on any change in the law.
Dennis Wilson, Zatra Consultants Limited
Dennis WilsonChief Operating Officer, Zatra Consultants Limited

Engineer. Execution of registrations, licences and authority follow-up. Ten years in operations and industrial engineering.