EWURA licence Tanzania: selling power from idle generators and solar roofs.

When an idle generator or a solar roof can earn without an EWURA licence, when it cannot, what the register fees are and how Zanzibar differs.

Engineers reviewing plans on site
DEAL DESK GUIDE
16minute read
11sources cited
8questions answered
Direct answer

Do I need an EWURA licence to sell electricity from my generator or solar roof in Tanzania? On the Mainland, generation and supply of electricity need an EWURA licence under the Electricity Act, 2008, section 8. Rural generation below 1 MW at one site is exempt from the licence, though below-1 MW projects must still register. Renting out a generator or a roof for a fixed fee is a different question that EWURA should confirm in writing.

Engineers reviewing plans on site
A generator or a roof earns two ways: rent for the equipment or the space, or a price per kilowatt-hour. The law treats them differently.

What the law says: who needs an EWURA licence in Tanzania

An EWURA licence Tanzania owners need depends on what the asset sells. Section 8(1) of the Electricity Act, 2008 (Cap. 131) lists the activities that require a licence: generation, transmission, distribution, supply, system operation, cross-border trade, physical and financial trade in electricity, and electrical installation. The Act defines generation as the production of electric energy from any primary source and supply as the sale of electricity to consumers. Operating without a licence is an offence under section 8, with a fine of up to TZS 10,000,000, imprisonment of up to five years, or both.

Section 2 limits the Act to the Mainland. The regulator is the Energy and Water Utilities Regulatory Authority, EWURA. Zanzibar has its own regulator, covered in a separate section below.

The Act does not use the words generator hire or roof lease. That gap is where most idle-asset questions sit, and the rest of this guide sorts them into settled, to verify and unknown.

Who should read this

Owners of standby and prime-power generators that sit idle between projects. Owners of warehouses, factories, hotels, schools and farm buildings with unshaded roofs. Contractors and camps that need power without buying a plant. Installers and solar developers looking for roofs. Lenders and valuers asked to finance or value such assets. Advocates and accountants advising any of them. If you only want to run your own plant for your own use, much of this still applies, because the fees and the registration rule differ for own-use plant.

This guide is general information. It does not replace a written confirmation from EWURA or an advocate's opinion on your facts.

Is hiring out a generator the same as selling electricity?

Not on the wording of the Act, but the line is a matter of facts. The two models differ in who runs the plant and what is priced.

ModelWho operates the plantWhat the customer pays forLikely licence position
Dry hireThe hirer, with own fuel and operatorA daily or monthly rate for the machineHirer generates for own use; owner is a lessor. Verify with EWURA
Wet hire with operatorThe owner's operatorA rate for machine and operator, fuel as agreedCloser to a service; verify, especially if the customer is billed by output
Metered saleThe ownerA price per kilowatt-hourGeneration and supply: licence unless an exemption applies
Solar roof leaseThe installer or the roof ownerRent for roof space, or a price per kilowatt-hourRent: verify. Per-kWh sale: licence or exemption

Settled: a price per kilowatt-hour to a customer is a sale of electricity. To verify: whether a flat rental of the machine, with the hirer operating it, is outside section 8. The Act's definitions point that way, because the hirer produces the power and the owner sells none. No EWURA ruling on generator hire was found for this guide, so it should be requested in writing before an owner relies on it.

Is a plant below 1 MW exempt from an EWURA licence?

Only in part. Section 18(1) lets EWURA exempt any person from section 8. Section 18(3) exempts generation in rural areas where installed capacity at a single site is below one megawatt, and section 18(4) exempts off-grid distribution and supply in rural areas where maximum demand is below one megawatt. The exemption is tied to rural areas. The Act text read for this guide does not define rural, and a site in a municipal or township area should not assume the exemption.

EWURA's own Electricity Sub-Sector Regulatory Information Booklet (fourth edition, October 2025) says the same and adds that exempt projects below 1 MW must still register. It cites rule 37(1) of the Electricity (Development of Small Power Projects) Rules, 2020, which requires registration of generation and distribution projects below 1 MW.

The fee register also carries a licence fee for generation below 1 MW, which confirms that licensed projects of that size exist. Treat a rural site below 1 MW as registered, not unregulated.

What is a small power project and how does selling to TANESCO work?

EWURA's booklet applies the 10 MW mark to small power projects: standardised power purchase agreements and tariffs for projects up to 10 MW selling to the main grid or to mini grids, under sections 23 and 25 of the Electricity Act. The Standardised Power Purchase Agreement runs for up to 20 operating years from the commercial operation date. A developer must conclude it within 90 days after the distribution network operator delivers an interconnection cost statement. For projects above 10 MW, EWURA approves purchase prices. A Tanzania law-firm guide, the ALN Power Guide: Tanzania, describes small power producers as undertakings generating up to 10 MW, in line with EWURA.

That guide also contains a sentence on approval thresholds for small power projects that contradicts its own definition, so the lower threshold for any approval exemption should be verified with EWURA before it is relied on. For an idle generator, the practical point is simpler: selling to TANESCO is a project with a licence, an interconnection study and a 20-year contract, not a quick hire.

How does net metering fit a solar roof?

The Electricity (Net-Metering) Rules, 2018, GN No. 76 published on 2 March 2018, apply to generating facilities below 1,000 kW. The customer and the distributor sign a Standard Interconnection Agreement. The distributor installs a bidirectional meter at its own expense and bills monthly. Energy exported in excess of energy imported earns kWh credits carried to the next period. Credits expire after three years, and no cash is paid. Enrolment is first come, first served until total net-metered capacity reaches five percent of the previous year's highest peak load, though the distributor may offer more.

Net metering fits a roof owner who consumes the power on site. It does not make the roof owner a seller. The Rules as read do not say whether a generation licence is also required, so that point is unknown and belongs in the written question to EWURA. A third party that owns the panels and sells the output to the building is a different model, because the price per kWh is a sale.

What does a solar roof lease need in law?

A roof lease is a lease of part of a building. The owner needs title or the owner's consent, any lender's consent, and a lease that states the installer's right to access, the fixing method, removal at the end, insurance and who bears roof damage. The warehouse leasing checklist covers the building-side checks, and movable assets as collateral explains why an installer's panels should be registered as the installer's security, not left as fixtures the roof owner's bank can claim.

A solar installation also needs an environmental decision. A Zatra guide on solar mini-grids and captive power, published on 10 September 2026, notes that a NEMC environmental certificate is not an EWURA licence and a TANESCO connection offer is not one either. Each is a separate approval, and none replaces the others. If the installer sells per kilowatt-hour, the licence or exemption question comes before the build, not after it.

What do EWURA licence fees cost?

The fees below come from the Zatra government fee register, which cites the Electricity (Licensing and Registration Fees) Rules, 2022, GN 112 of 4 March 2022. They are government fees, paid to EWURA against a control number, separate from Zatra's professional fee. EWURA may assess other amounts, so the control number governs on the day of payment. The full register is at zatra.co/guides/government-fees.

Item (register ID)ApplicationSecond feeLicenceTransfer or change
Generation below 1 MW (F0637)TZS 100,000TZS 100,000TZS 100,000TZS 100,000
Generation 1 to 10 MW (F0638)TZS 100,000TZS 240,000 (base provisional)TZS 12,000,000TZS 1,200,000
Own-use baseload below 1 MW (F0644)TZS 100,000TZS 100,000TZS 200,000TZS 100,000
Own-use standby generation (F0645)TZS 100,000none listedTZS 200,000TZS 100,000

Supply and distribution licences use the same bands (F0641). The annual regulatory levy is 1% of gross operating revenues for electricity (F0663). A Class A business licence for electricity production or distribution is listed at TZS 1,000,000 for the principal place and TZS 600,000 for each branch, with USD 5,000 and USD 2,000 for foreign-owned businesses (BLA078 and BLA079). Whether that licence applies to a generator-hire business is not settled and should be confirmed with BRELA.

How are hire, rent and electricity sales taxed and papered?

Tax needs an accountant, and the points here are for orientation. The VAT standard rate is 18% (F0239), with registration at taxable turnover of TZS 200 million in 12 months. The corporate rate is 30% (F0196). The Clyde and Co note on the Finance Act 2026, published on 3 July 2026, did not report a change to either rate, and it did not mention solar or generators.

Withholding on rent depends on the asset: 10% on rent of land and buildings (F0214), which covers a roof lease, and 10% on construction equipment or machinery (F0216). Rent of other assets to residents is outside withholding (F0218). Whether a generator counts as construction equipment depends on its use, which an accountant should confirm.

Stamp duty on a lease is 1% of the annual reserved rent, and from the Finance Act 2026 the definition of lease includes movable property (F0265). A hire agreement for a generator is therefore likely to attract it. Have an advocate draft the contract, and see the guides on hiring out construction equipment and lease finance for the wet, dry and finance structures.

A worked example: three generators and one roof in Mwanza

A factory owner in Mwanza has three idle 250 kVA generators and a 1,000 square metre roof. All figures are illustrative bands, not quotes.

RouteAssumptionAnnual grossGovernment items
Dry hire of three generatorsTZS 2,000,000 per generator per monthTZS 72,000,000Stamp duty 1% of annual rent: TZS 720,000 (F0265); VAT 18% if registered (F0239)
Roof lease to an installerTZS 2,000,000 a monthTZS 24,000,000Stamp duty TZS 240,000 (F0265); 10% withholding of TZS 2,400,000 if the tenant is a withholding agent (F0214)
Solar sold per kWh, roof developed by the ownerAbout 150 kW installed, 1,400 kWh per kW a year, TZS 300 per kWh210,000 kWh gives TZS 63,000,000Levy 1%: TZS 630,000 (F0663); generation licence below 1 MW: TZS 100,000 each for application, second fee and licence (F0637)

The per-kilowatt-hour price is a placeholder, not a TANESCO or EWURA tariff. The owner who only rents out machines and space avoids the sale of electricity, which is why EWURA's written view matters before that route is chosen. The owner who sells kilowatt-hours takes on licensing, metering, billing and customer disputes. The dry hire route needs only an agreement, insurance and, where required, the hirer's own-use registration.

What changes in Zanzibar under ZURA?

Everything on this page so far is Mainland law. The Electricity Act, 2008 applies to the Mainland only under section 2. In Zanzibar, the Zanzibar Utilities Regulatory Authority regulates electricity under the Zanzibar Utilities Regulatory Authority Act, Act No. 7 of 2013, according to the ALN Power Guide: Zanzibar. That guide says a developer needs a provisional licence from ZURA for preparatory work and then an electricity generation licence, and that ZURA must approve a power purchase agreement and its tariff before the Zanzibar Electricity Corporation signs it. Wikipedia's note on ZURA says it was established in 2015 under that Act.

Unknown: whether Zanzibar has any exemption threshold like the Mainland 1 MW rural rule, and what ZURA charges. The ALN guide mentions none, and the fee register does not list ZURA electricity fees. Do not apply the Mainland figures in Zanzibar. A Mainland EWURA licence or a Mainland registration does not cover a Zanzibar site.

What can go wrong with generator and roof deals?

  • Billing per kilowatt-hour under a hire agreement, which turns equipment hire into a sale of electricity.
  • Assuming the rural 1 MW exemption applies to a town site.
  • Skipping the below-1 MW registration under the 2020 Small Power Projects Rules.
  • Treating a NEMC certificate or a TANESCO offer as the EWURA licence.
  • A generator under a bank charge, hired out without the lender's consent.
  • Panels fixed to a roof the owner does not control, or whose lender has not consented.
  • Cash-in-hand rent with no invoice, which leaves no record for the tax or the licence file.
  • Selling surplus power to a neighbour over the fence, which is supply and distribution.

An offence under section 8 carries up to TZS 10,000,000, up to five years, or both, so the written EWURA position is cheaper than the risk.

Which questions should the letter to EWURA or ZURA ask?

A written question gives an owner something to show a lender, a hirer and an advocate. Keep it short, state the facts, and ask for a reply on the regulator's letterhead. The letter should give the owner's legal name and registration, the site and whether it is on the Mainland or in Zanzibar, whether the area is rural or urban, the installed capacity at the single site in kilowatts, the equipment and its serial numbers, and who will operate it.

Then ask closed questions. Does renting the machine for a fixed fee, with the hirer operating it, need a licence from the owner? Does a roof lease to an installer need any approval from the owner? If power is sold per kilowatt-hour, is a generation licence, a supply licence or an exemption needed at this size and place? Must the project register under the 2020 Small Power Projects Rules? Is own-use registration needed for the hirer? What is the expected processing time?

Keep the reply, the date and the name of the officer in the deal file. A reply is the regulator's view on those facts at that date. It is not a guarantee of a later decision, and a change in facts, such as a larger plant or a new customer, needs a fresh question.

What do lenders, insurers and valuers ask about an energy asset?

Whoever funds or insures the asset reads the licence position before the price. A lender holding a charge over a generator asks for consent before any hire and for the hirer's insurance. An insurer asks who operates the plant, where it stands and whether use for hire is on the policy, because a policy written for the owner's own use may not respond when a hirer runs the machine. A valuer from the independent expert panel values the equipment by age, hours run, service history and condition, and an engineer confirms output and safety.

For a solar roof, the roof owner's lender may refuse a long installer lease that binds a future buyer. The installer's lender will ask whether the panels are registered as the installer's security. If power is sold, a lender will also ask for the licence or exemption letter, the customer's contract, the metering method and the credit risk of the customer. A signed hire or power agreement is evidence a bank can read, but it is the owner's own lender who decides. Fursa365 does not lend and does not take part in that decision.

An owner who prepares title, insurance, a valuation and the EWURA reply before the first meeting saves weeks. A file without them is returned at screening.

What does a Fursa365 energy offer or request look like?

An offer lists the asset, its location by region, its capacity in kVA or kW, the age and service record, the route (dry hire, wet hire, roof lease or power sale), the price as a band, the minimum term and an end date. Serial plates and exact addresses stay out of the public view until the NDNCA is signed. The evidence list includes title or proof of mandate, any lender consent, insurance, photos taken this month and the EWURA or ZURA reply.

A request states the load in kW, the hours needed, the site, the start date, the budget band and whether the requester will operate the machine. Zatra verifies the requester's identity, mandate and capacity before a match. Parties may ask for an engineer's report on the generator or a roof survey from the independent expert route. If several buyers want the same generator, a sealed-bid round is an option under the sealed bids guide.

See the NDNCA explained and the business deals page for how a match becomes a signed agreement. Fursa365 introduces; the parties negotiate, pay each other directly and take their own advice.

What to do now

  1. Decide what you sell: the machine, the space or the kilowatt-hour. Write it in one sentence.
  2. Confirm the site: Mainland or Zanzibar, rural or urban, installed capacity at the single site, and any lender's charge.
  3. Ask EWURA in writing whether your model needs a licence, registration or an exemption, and keep the reply. In Zanzibar, ask ZURA.
  4. Collect the evidence: ownership or title, serial plates, service records, roof drawings, insurance and photos taken this month.
  5. Price as a band with a minimum term, a deposit and an end date on the offer.
  6. List on Fursa365 under the idle assets category, or post a verified request if you need power.
  7. Accept a match from demand that Zatra has verified.
  8. Sign the NDNCA before names move, then run your own due diligence.
  9. Have an advocate draft the agreement: hire, roof lease or power sale, with licence status as a condition.

Key dates

ItemDate or period
Net-Metering Rules, GN 76Published 2 March 2018; agreement term 20 years
EWURA fee rules, GN 1124 March 2022
Standardised Power Purchase AgreementUp to 20 operating years; conclude within 90 days of the interconnection cost statement
Net-metering creditsExpire after three years
Finance Act 2026 changes, including stamp duty on movable leasesFrom 1 July 2026
Fursa365 offer end date30 to 90 days suits most hire and roof offers

How Zatra helps

Zatra Consultants Limited screens the owner's right to offer, the title, any lender's charge and the evidence before a listing is shown, and verifies demand before a match. As adviser under a PSFA, Zatra structures the hire, roof lease or sale, prepares the written question to EWURA or ZURA, and coordinates the advocate, accountant and engineer. Fursa365 matches; it does not lend, hold money or act as a broker, and the parties pay each other directly. The success fee is a professional fee, not brokerage, and government fees are paid to the authority at the official rate. Zatra does not insure, license, value or lend, and does not decide or guarantee any authority's outcome. EWURA, ZURA, TANESCO and NEMC decide their own matters. See regulatory boundaries, verification and the idle assets page.

Sources and status

Accurate as at 18 Nov 2026. Figures are from the sources below and from the Zatra government fees register, quoted with their register IDs so they can be checked line by line.

Figures to confirm before you act

  • Section 8(5) Electricity Act penalty: up to TZS 10,000,000, five years, or both
  • EWURA generation below 1 MW fees TZS 100,000 each (register ID F0637)
  • EWURA generation 1 to 10 MW licence TZS 12,000,000 (F0638)
  • Own-use standby licence TZS 200,000 (F0645)
  • EWURA annual levy 1% of gross operating revenues (F0663)
  • Net-metering ceiling 1,000 kW and five percent of previous peak load
  • Stamp duty on a lease 1% of annual rent (F0265)
  • Withholding on rent 10% (F0214, F0216)
  • Class A electricity business licence TZS 1,000,000 / 600,000 (BLA078)
  • The illustrative TZS per generator per month, yield and tariff in the worked example

General information prepared by the Fursa365 deal desk, Zatra Consultants Limited. It is not legal, tax or investment advice and does not decide or guarantee any authority's outcome. Confirm current rules and fees with the authority named and your own advocate before you act. Mainland Tanzania is described; Zanzibar has separate laws and bodies.

Questions readers ask

Do I need an EWURA licence to hire out a generator?

The Electricity Act requires a licence to generate or supply electricity. A flat rental where the hirer runs the machine does not obviously fall within either. No EWURA ruling on this was found, so ask EWURA in writing and keep the reply.

Is a rooftop solar system below 1 MW exempt?

Section 18(3) exempts rural generation below 1 MW at one site. A building in a town is not clearly covered. Below-1 MW projects must still register under the 2020 Small Power Projects Rules, and EWURA's booklet says so.

Can I sell power to my neighbour?

Selling electricity to a customer is supply, and moving it over lines is distribution. Both are licensed activities unless an exemption applies. Rural off-grid supply with maximum demand under 1 MW is exempt under section 18(4), so location decides.

What does net metering allow?

A customer with a facility below 1,000 kW can export to the distributor and earn kWh credits against later bills. Credits expire after three years, and no cash is paid. It reduces the owner's bill; it is not a sales licence.

Is a NEMC certificate enough?

No. An environmental certificate and a TANESCO connection offer are separate approvals. Neither is an EWURA licence, and the licence or exemption question should be answered before building.

How much is a small generation licence?

The register lists TZS 100,000 each for application, second fee, licence and transfer for generation below 1 MW. From 1 MW to 10 MW the licence is TZS 12,000,000. The control number issued by EWURA governs.

Does a Mainland licence cover Zanzibar?

No. Zanzibar electricity is regulated by ZURA under Act No. 7 of 2013, and the Electricity Act applies to the Mainland only. Ask ZURA about licensing and any exemption for a Zanzibar site.

Who pays Fursa365 for a match?

Listing and matching are free. If you engage Zatra to structure the deal, the professional fee is paid under a PSFA, separate from government fees. Fursa365 never holds money, and the parties pay each other directly.

Seen an error or a changed fee? Write to [email protected] with the guide title and the line. The desk reviews every guide quarterly and on any change in the law.
Dennis Wilson, Zatra Consultants Limited
Dennis WilsonChief Operating Officer, Zatra Consultants Limited

Engineer. Execution of registrations, licences and authority follow-up. Ten years in operations and industrial engineering.

Ready to act on this guide?

Submit a qualified offer or a verified request. Zatra screens it; only verified counterparties ever see it.